Vessel chartering for project cargo

part and full charters for out-of-gauge cargo

  1. Cargo list
  2. Tonnage
  3. Fixture
  4. Loading
  5. Settlement

Chartering a vessel for project cargo pays off when the parcel is too large or heavy for liner sailings or when delivery dates are tied to the construction schedule. We source tonnage, negotiate freight and the charter party and follow the vessel from arrival to discharge.

In chartering, money is most often lost on laytime: if the cargo is not ready when the vessel arrives or loading runs slower than agreed, demurrage accrues. That is why we tie the laycan to cargo readiness and port capabilities in advance.

Tell us the route, cargo and container type.
02

Specification

updated 2025-Q4 · form ATF-PROJECT-CHARTER-2025

Specification · Vessel chartering. Standard terms · vessel, laycan and freight are fixed in the charter party

Service

Type
voyage charter: part or full
Cargo
project parcels, out-of-gauge, heavy lifts
Options
lashing plan, survey, cargo insurance

Terms

Timing
search and fixture — typically 1–3 weeks
Form
GENCON / HEAVYLIFTVOY
Currency
USD / RUB

Logistics

Before fixing
cargo list, tonnage, negotiation
At port
NOR, loading, statement of facts
After
discharge, laytime calculation

Price

Base
lumpsum or per-tonne freight
Extras
demurrage, port dues, lashing — at cost
03

Service flow

5 steps
  1. 01

    Enquiry and cargo list

    We collect a per-piece cargo list, loading and discharge ports, the desired vessel window and loading conditions at the shipper's side.

    1–3 days
  2. 02

    Tonnage search

    We go to the market through brokers and operators, collect vessel offers and check each: cranes, hatches, deck strength, hold capacity and the vessel's position for the required dates.

    3–14 days
  3. 03

    Negotiation and fixture

    We agree freight, laycan, loading and discharge terms, laytime, demurrage rate and payment terms. Once subjects are lifted the vessel is fixed and the charter party is signed.

    2–7 days
  4. 04

    Arrival and loading

    The vessel tenders its notice of readiness (NOR) and laytime starts to count. We supervise loading and securing per plan, keep the statement of facts and obtain the bill of lading.

    per laycan
  5. 05

    Voyage, discharge, settlement

    Direct voyage to the destination port, discharge under survey, laytime calculation for both ports and settlement of demurrage or despatch.

    voyage + 1–3 days
04

Problems

3 situations
01 · Problem

The factory misses the laycan: the vessel waits at the berth, demurrage runs and, at worst, dead freight is charged for the short-shipped cargo.

→ ATF solution

We set the laycan against confirmed cargo readiness with a buffer and track production before fixing the vessel.

02 · Problem

Loading is slower than the charter party assumes, and laytime runs out before the cargo is on board.

→ ATF solution

Loading rates are agreed with the port and stevedore before fixing; on site we keep the statement of facts and dispute unjustified hours.

03 · Problem

The bank rejects the charter party B/L under the letter of credit because the L/C was drafted for a liner shipment.

→ ATF solution

Before the L/C is opened we agree with the buyer and the bank that a charter party B/L is acceptable.

05

Documents

2 blocks

Documents of a charter deal. Loading and discharge terms (FIO, liner terms), laytime and the demurrage rate must be agreed so that they do not contradict the sales contract.

Incoterms

FOB
the buyer charters the vessel — the laycan must match the delivery date in the contract
CFR / CIF
the seller charters; discharge and demurrage at destination follow the contract
FAS
seller places the cargo alongside; loading is on the buyer and the vessel

Documents

Cargo list
each piece: dimensions, weight, CoG, deck-stowable or not
Charter party
usually on the GENCON form, HEAVYLIFTVOY for heavy lifts
Fixture recap
summary of agreed terms after fixing
NOR & Statement of Facts
the basis for laytime and demurrage calculation
Bill of lading
charter party B/L referring to the charter
06

FAQ

6 questions

In a part-charter you hire part of the vessel for your parcel, and the operator sells the rest of the space to other cargo. In a full charter the ship works only for you. A full charter gives freedom on dates and ports; a part-charter saves money when the cargo does not fill the ship.