09Project logistics & oversize· Handling · upending

Rigging and transshipment of oversize cargo

upending, SPMT moves, foundation set-down

  1. Site visit
  2. Method statement
  3. Preparation
  4. Operation
  5. Handover

Rigging and transshipment of oversize cargo is the riskiest part of a project move: cargo is damaged more often during handling than in transit. We transship heavy units between vessel, rail and low-bed, upend them to erection position and move them on SPMT and skates to a method statement.

Long units such as columns and reactors are upended with two cranes: the main crane lifts the top while the tailing crane guides the bottom until the unit stands upright. The scheme is calculated around the centre of gravity so the shell takes no bending loads.

Tell us the route, cargo and container type.
02

Specification

updated 2025-Q4 · form ATF-PROJECT-HANDLING-2025

Specification · Rigging and transshipment. Standard terms · method and equipment are confirmed after a site visit

Service

Operations
transshipment, upending, moving, set-down
Locations
port, rail station, site, workshop
Options
survey, operation insurance, storage

Terms

Preparation
typically 1–2 weeks before
Documents
method statement and condition report included
Currency
RUB / USD

Logistics

Before
site visit, method statement, equipment
Operation
transfer or upending, photos
After
set-down, report, handover

Price

Base
per operation, per method statement
Extras
mats, equipment idle time, storage — at cost
03

Service flow

5 steps
  1. 01

    Data and site visit

    We study the cargo drawing, the work location and the transport in and out: vessel, wagon, low-bed, storage or foundation. We inspect the site, surface and access.

    1–3 days
  2. 02

    Method statement

    We develop the method statement: transshipment or upending method, equipment, CoG and support-load calculation, sequence and danger zones.

    2–5 days
  3. 03

    Equipment and preparation

    We line up cranes, SPMT, jacks and skates, prepare the rigging and the ground: mats, levelling, travel paths.

    2–7 days
  4. 04

    Operation

    We carry out the transshipment, upending or move under the works manager; the surveyor records cargo condition before and after.

    hours to 2 days
  5. 05

    Set-down and handover

    We set the cargo on the cradle, vehicle or foundation, check its position and sign the report handing it over to the next party in the chain.

    on the day
04

Problems

3 situations
01 · Problem

A long column is upended with a single crane — the shell bends and nozzles and internals get damaged.

→ ATF solution

We upend with two cranes or an upending frame to calculation, using lifting points agreed with the manufacturer.

02 · Problem

The SPMT or low-bed cannot pass through the site: the surface cannot take the load, radii are tight, poles and cables are in the way.

→ ATF solution

We check the path in advance, calculate surface pressure, lay mats and relocate obstacles if needed.

03 · Problem

Cargo is handled twice via storage because onward transport is not ready — extra lifts, storage and risk.

→ ATF solution

We synchronise transport with cargo arrival and work direct transfer wherever possible.

05

Documents

2 blocks

Documents for a handling operation. At every mode change the cargo passes from one party to another, so a condition report with photos before and after is the main protection in a damage dispute.

Incoterms

FAS
the seller delivers alongside — handling on the quay is on the seller
FOB
the seller is responsible until loaded on board
DPU
the seller unloads at the destination

Documents

Cargo drawing
weight, CoG, support and lifting points
Method statement
sequence, equipment, upending scheme
Rigging certificates
for spreaders, slings, shackles
Condition report
with photos before and after
Completion certificate
noting the cargo handover
06

FAQ

6 questions

Rigging is lifting, moving and placing heavy equipment: slinging, crane transfers, moving on skates and with winches, bringing units through openings into a workshop, setting on foundations. Work follows a method statement with a centre-of-gravity calculation. We organise rigging as a stand-alone operation or as part of a project move.