Cargo securing plan

lashing plans for sea, rail and road

  1. Data
  2. Calculation
  3. Drawing
  4. Approval
  5. Check

A cargo securing plan is a calculation, not a set of straps applied by experience: for each piece we determine the forces that will slide and tip it and the lashings that will hold it. We develop the lashing plan for the specific vehicle, get it approved and check it at loading.

The rules differ by mode: at sea — the IMO CSS Code and the ship's Cargo Securing Manual, on rail — the Technical Conditions for cargo placement and securing, and on road the calculation usually follows EN 12195-1.

Tell us the route, cargo and container type.
02

Specification

updated 2025-Q4 · form ATF-PROJECT-LASHING-2025

Specification · Securing plan. Standard terms · timing is confirmed once cargo drawings and vehicle data are received

Service

Vehicle
ship, rail flatcar, low-bed, MAFI, flat rack
Deliverable
drawing, calculation, material list
Options
lashing material, crew, survey

Terms

Timing
typically 3–7 working days after drawings
Approval
with vessel or carrier included
Currency
RUB / USD

Logistics

Before loading
data, calculation, drawing
Approval
master / carrier / RZD
At loading
check, lashing certificate

Price

Base
fixed fee per unit or parcel plan
Extras
lashing material, stopper welding, survey — on request
03

Service flow

5 steps
  1. 01

    Input data

    We collect the cargo drawing with weight, CoG and supports, the vehicle data (for a ship — the Cargo Securing Manual and lashing points, for rail — the flatcar type), route and season.

    1–2 days
  2. 02

    Force calculation

    We calculate longitudinal, transverse and vertical forces for the chosen position, taking friction, wind and impacts into account. We select lashings by working load (MSL/LC), their number and angles.

    1–3 days
  3. 03

    Drawing and material list

    We issue the drawing: stowage, cradles, stoppers, lashing positions and angles, and the material list. For sea we specify separately what is welded to the deck.

    1–2 days
  4. 04

    Approval

    We agree the plan with the master or superintendent, with the road carrier or under RZD rules; for a non-standard rail securing method, separate drawings and calculations are approved through the prescribed procedure.

    1–5 days
  5. 05

    Execution check

    At loading the surveyor checks the securing against the plan and issues a certificate. On road moves the tension is re-checked after the first kilometres and at stops.

    on loading day
04

Problems

3 situations
01 · Problem

The cargo was secured by eye, shifted in a storm or under braking — and the insurer disputes the claim, citing improper securing.

→ ATF solution

We secure to calculation, and a surveyor confirms it with a certificate — evidence of proper securing.

02 · Problem

The cargo has no built-in lashing points, or they are not rated for the required force.

→ ATF solution

We agree the points with the manufacturer in advance; if there are none, we secure with loops over cradles and stoppers without loading the casing.

03 · Problem

The wagon is detached at a station because the placement and securing do not comply with the Technical Conditions.

→ ATF solution

We calculate the scheme to the TU, and non-standard securing methods are approved through the prescribed procedure in advance.

05

Documents

2 blocks

What is needed for the calculation and what is handed over. The delivery term and freight terms decide who pays for lashing material and labour — settle it before loading.

Incoterms

EXW
the buyer arranges loading and securing at the factory
FCA
the seller loads at its premises — securing should be spelled out in the contract
FOB
securing on board follows the freight terms (e.g. FIOSLSD — at the cargo side's cost)

Documents

Cargo drawing
weight, CoG, bearing surfaces, built-in lashing eyes
Vehicle data
for a ship — Cargo Securing Manual and deck points
Lashing Plan
drawing with stowage, lashings, angles and stoppers
Calculation
force balance and margin in each direction
Lashing certificates
MSL / LC of chains, straps, turnbuckles, shackles
Lashing certificate
surveyor's confirmation that the plan was carried out
06

FAQ

6 questions

A lashing plan is a calculated scheme for stowing and securing cargo on a vehicle. It shows that the cargo will not slide or tip under ship motions, braking or wind. Carriers and insurers require it for project cargo, and the surveyor's certificate against it is the key argument in a damage dispute.