07Project logistics & oversize· Special permits · OSOW

Special permits for

oversize and heavy road moves

  1. Parameters
  2. Application
  3. Approvals
  4. Permit
  5. Move

A special permit for an oversize load is required when the loaded vehicle exceeds the permitted dimensions, weight or axle load — as set by Article 31 of Federal Law No. 257-FZ on Roads. We calculate the vehicle combination, lay out the route, file the application and handle all approvals until the permit is issued.

The permit is tied to a specific vehicle combination and route. Swapping the tractor or trailer, leaving the route or exceeding the load at a weigh-in-motion station means a fine and a stopped move, so we fix the parameters precisely.

Tell us the route, cargo and container type.
02

Specification

updated 2025-Q4 · form ATF-PROJECT-PERMITS-2025

Specification · Special permits. Standard terms · timing depends on the number of approving bodies on the route

Service

Permits
for oversize and heavy vehicles
Approvals
roads, bridges, RZD, power lines, traffic police
Options
route survey, escort

Terms

Timing
typically 2–4 weeks, longer with bridge assessment
Filing
Rosdormonitoring or regional authority
Currency
RUB

Logistics

Preparation
vehicle, axles, route
Processing
application, approvals, payment
Move
pilot car, obstacle removal

Price

Base
permit processing — fixed fee
Extras
damage fee, escort, wire lifting — at cost
03

Service flow

5 steps
  1. 01

    Vehicle parameters

    We select the vehicle combination for the cargo and calculate loaded dimensions, gross weight and load per axle. We compare them with the limits to see which permit is needed — oversize, heavy or both.

    1–2 days
  2. 02

    Route and application

    We lay out the route around bridge, overpass and power-line limits, after a route survey if needed. The application goes via the FKU Rosdormonitoring portal or to the regional authority, depending on whose roads the route uses.

    2–5 days
  3. 03

    Approvals

    The application is approved by the road owners along the route and, for oversize vehicles, by the traffic police. In parallel we obtain RZD approval for level crossings and power-line owners' consent. We answer queries and resolve comments.

    typically 2–4 weeks
  4. 04

    Payment and issue

    For a heavy vehicle the road-damage compensation is paid, after which the permit is issued with the route, validity and movement conditions: time, speed, escort.

    1–3 days
  5. 05

    Escorted move

    We run the move under the permit conditions: pilot car or traffic-police escort, wire lifting and sign removal at tight spots, movement within the permitted hours.

    per route
04

Problems

3 situations
01 · Problem

The permit was issued for one vehicle combination, but a different tractor or trailer turned up on the day — a fine and a stop at the weigh station.

→ ATF solution

We lock in the specific vehicles with the carrier before applying and re-issue the permit before departure if anything changes.

02 · Problem

A bridge owner refuses approval or requires an assessment of the structure.

→ ATF solution

We spread the weight over more axles, find a detour or build the assessment into the timeline in advance.

03 · Problem

The cargo is already in port but the haulage permit is not ready — storage charges pile up.

→ ATF solution

We file the application in parallel with the sea leg as soon as the cargo and vehicle parameters are known.

05

Documents

2 blocks

The set for a special-permit application. The permit is issued for a specific vehicle combination and route: if the tractor, trailer or route changes, it must be re-issued.

Incoterms

FCA
haulage from the seller and its permits are the buyer's concern
DAP
the seller or its carrier obtains permits to the destination
DPU
the same plus unloading at site — the site must be included in the route

Documents

Vehicle combination diagram
loaded dimensions, axle spacing, load on each axle
Vehicle documents
registration certificates and vehicle passports (EPTS) of tractor and trailer
Cargo details
drawing or data sheet with weight and dimensions
Route
points, roads and towns along the way
Damage fee payment
payment confirmation for a heavy vehicle
06

FAQ

6 questions

When the loaded vehicle exceeds the permitted dimensions, gross weight or axle load set by the Rules for the Carriage of Goods by Road. Dimension benchmarks: 2.55 m wide, 4 m high, 20 m long for a road train. Without a permit such movement is prohibited by Article 31 of Law No. 257-FZ.